502 Hay Street

Site: 502 Hay

Site Address: 502 Hay Street, Subiaco WA

Principal: Dradgin

Services: BMS; EMS; Service and Maintenance

summary

Leopard Controls has successfully completed the BMS upgrade project for the building at 502 Hay Street, addressing multiple controller failures and issues that arose from a historic maintenance regime. As an experienced BMS contractor, Leopard enhanced the BMS system’s efficiency, control, and monitoring capabilities, optimizing energy consumption and improving occupant comfort. Key tasks included conducting a dilapidation assessment of ventilation and air conditioning equipment, decommissioning and staging the replacement of main Schneider controllers to avoid tenant disruption and installing an Optergy Energy Management System (EMS) for billing and reporting on electrical, gas, and water meters. The project also involved the installation of Distech Controls BACnet intelligent controllers and a complete Headend featuring a web-based platform powered by the Niagara N4 Framework®, resulting in a modern and effective BMS solution.

solution

The project consists of an integrated BMS and DDC control system which includes:

  • IP Network Back Bone
  • Distech Controls DDC Controls Design & Installation of Critical Equipment
  • Integration of Schneider VAV Controllers
  • BACnet Open Systems Integration
  • Circa 1500 BMS Points
  • Niagara N4 Open Systems BMS Front End
  • Optergy EMS Front End
  • Extensive monitoring and integration of electrical and Hydraulic services
  • Remote Web based access & SMS link for critical alarms.